What actually slows down a project?

Unread post by HerrTick »

I the past (and, almost certainly, the future), I spoke derisively about users who try way too hard to minimize mouse-clicks and feature count. While these things measure CAD gamesmanship, these things are never what accelerates a project.

CAD acumen is not tested by what you can make, but what you can change. Can your CAD models stand up to the twists and turns of unforeseen changes that inevitably crop up on the path from drunken marketing feverdream to final delivery?
User avatar
bnemec
Posts: 1954
Joined: Tue Mar 09, 2021 9:22 am
Answers: 10
Location: Wisconsin USA
x 2562
x 1411

Re: What actually slows down a project?

Unread post by bnemec »

HerrTick wrote: Mon Feb 07, 2022 2:19 pm I the past (and, almost certainly, the future), I spoke derisively about users who try way too hard to minimize mouse-clicks and feature count. While these things measure CAD gamesmanship, these things are never what accelerates a project.

CAD acumen is not tested by what you can make, but what you can change. Can your CAD models stand up to the twists and turns of unforeseen changes that inevitably crop up on the path from drunken marketing feverdream to final delivery?
What you speak of becomes so much more important when all files are part of the "Standard Parts Library" and have an unknown scope.
User avatar
matt
Posts: 1592
Joined: Mon Mar 08, 2021 11:34 am
Answers: 19
Location: Virginia
x 1219
x 2387
Contact:

Re: What actually slows down a project?

Unread post by matt »

For me, the big slow downs have been in order from biggest to smaller:

- Lost references
- waiting for decisions about the product or process
- getting clarifications on technical details
User avatar
jcapriotti
Posts: 1897
Joined: Wed Mar 10, 2021 6:39 pm
Answers: 32
Location: The south
x 1236
x 2029

Re: What actually slows down a project?

Unread post by jcapriotti »

In my experience:
  1. Setting unrealistic deadlines without input from those doing the work.
  2. Ignoring those users when they do ask.
  3. Undoing those decisions once they realize it isn't going to work.
......now back to year 5 of trying to get this global PLM system implemented. o[
Jason
User avatar
Jaylin Hochstetler
Posts: 387
Joined: Sat Mar 13, 2021 8:47 pm
Answers: 4
Location: Michigan
x 380
x 355
Contact:

Re: What actually slows down a project?

Unread post by Jaylin Hochstetler »

jcapriotti wrote: Mon Feb 07, 2022 3:24 pm In my experience:
  1. Setting unrealistic deadlines without input from those doing the work.
  2. Ignoring those users when they do ask.
  3. Undoing those decision once they realize it isn't going to work.
......now back to year 5 of trying to get this global PLM system implemented. o[
I wish I could like that post multiple times.
It is very true.
Makes me think of...
Engineers and Salesman.jpg
Edit to add: I was kinda surprised when I saw that meme in a SolidEdge blog: https://blogs.sw.siemens.com/solidedge/ ... figurator/
A goal is only a wish until backed by a plan.
User avatar
SolidMuse
Posts: 27
Joined: Mon Mar 15, 2021 4:44 pm
Answers: 0
Location: Arizona
x 90
x 66

Re: What actually slows down a project?

Unread post by SolidMuse »

Interruptions by anything, or person.... Stopping a train of thought and restarting again kills productivity.
User avatar
zxys001
Posts: 1079
Joined: Fri Apr 02, 2021 10:08 am
Answers: 5
Location: Scotts Valley, Ca.
x 2323
x 1001
Contact:

Re: What actually slows down a project?

Unread post by zxys001 »

HerrTick wrote: Mon Feb 07, 2022 2:19 pm I the past (and, almost certainly, the future), I spoke derisively about users who try way too hard to minimize mouse-clicks and feature count. While these things measure CAD gamesmanship, these things are never what accelerates a project.

CAD acumen is not tested by what you can make, but what you can change. Can your CAD models stand up to the twists and turns of unforeseen changes that inevitably crop up on the path from drunken marketing feverdream to final delivery?
Coffee Breaks! UU
"Democracies aren't overthrown; they're given away." -George Lucas
“We only protect what we love, we only love what we understand, and we only understand what we are taught.” - Jacques Cousteau
Frank_Oostendorp
Posts: 223
Joined: Tue Mar 09, 2021 7:25 am
Answers: 3
Location: Netherlands
x 185
x 230

Re: What actually slows down a project?

Unread post by Frank_Oostendorp »

Superfast SolidWorks operators, creating SolidWorks files in huge numbers in less time. After that, small errors are included in the files, there is no way to change/reuse these files, all parts are made with surfaces, way to complex features and over weighted. And all these files have to be re-created. grumph
User avatar
SPerman
Posts: 2080
Joined: Wed Mar 17, 2021 4:24 pm
Answers: 14
x 2256
x 1902
Contact:

Re: What actually slows down a project?

Unread post by SPerman »

[sarcasm]
image.png
image.png (45.15 KiB) Viewed 4126 times
[/sarcasm]
-
I may not have gone where I intended to go, but I think I have ended up where I needed to be. -Douglas Adams
Lapuo
Posts: 109
Joined: Tue Mar 09, 2021 2:06 am
Answers: 0
x 176
x 106

Re: What actually slows down a project?

Unread post by Lapuo »

Biggest slow down is hurrying up.
User avatar
Glenn Schroeder
Posts: 1527
Joined: Mon Mar 08, 2021 11:43 am
Answers: 23
Location: southeast Texas
x 1777
x 2142

Re: What actually slows down a project?

Unread post by Glenn Schroeder »

Useless meetings.
"On the days when I keep my gratitude higher than my expectations, well, I have really good days."

Ray Wylie Hubbard in his song "Mother Blues"
User avatar
bnemec
Posts: 1954
Joined: Tue Mar 09, 2021 9:22 am
Answers: 10
Location: Wisconsin USA
x 2562
x 1411

Re: What actually slows down a project?

Unread post by bnemec »

Frank_Oostendorp wrote: Tue Feb 08, 2022 6:45 am Superfast SolidWorks operators, creating SolidWorks files in huge numbers in less time. After that, small errors are included in the files, there is no way to change/reuse these files, all parts are made with surfaces, way to complex features and over weighted. And all these files have to be re-created. grumph
This.
User avatar
Tom G
Posts: 355
Joined: Tue Mar 09, 2021 9:26 am
Answers: 0
Location: Philadelphia, PA area
x 989
x 466

Re: What actually slows down a project?

Unread post by Tom G »

People.
User avatar
jcapriotti
Posts: 1897
Joined: Wed Mar 10, 2021 6:39 pm
Answers: 32
Location: The south
x 1236
x 2029

Re: What actually slows down a project?

Unread post by jcapriotti »

Meetings to prepared for the Meeting.
Jason
User avatar
DanPihlaja
Posts: 862
Joined: Thu Mar 11, 2021 9:33 am
Answers: 25
Location: Traverse City, MI
x 815
x 993

Re: What actually slows down a project?

Unread post by DanPihlaja »

jcapriotti wrote: Tue Feb 08, 2022 11:35 am Meetings to prepared for the Meeting.
Ahh, the ol' pre-meeting meeting. Yes....takes me back...
-Dan Pihlaja
Solidworks 2022 SP4

2 Corinthians 13:14
bradb
Posts: 29
Joined: Thu Mar 11, 2021 7:24 am
Answers: 0
Location: Ontario, NY
x 8
x 35

Re: What actually slows down a project?

Unread post by bradb »

From a mold designer " Here's my widget, go ahead and get started on the mold, I'm not done with the part design yet but I don't think too much will change".
User avatar
the_h4mmer
Posts: 136
Joined: Mon Jan 31, 2022 6:49 am
Answers: 1
x 106
x 80

Re: What actually slows down a project?

Unread post by the_h4mmer »

  • One person carrying the responsibility of 3 full time roles: design engineer, PDM/CAD admin, and 3D printing lead (I'm the only engineer)
  • Information bottle necks (or just no information)
  • Priorities shifting faster than the wind changes directions
  • Chasing shiny ideas for development projects

  • A broken PDM library (tons of out-of-context/broken references, out-of-band changes, assemblies released with unreleased parts, terrible check-in practices, little to no notes, etc.)
    - this all was done before I arrived at my current organization, and now I've inherited the mess, and no one wants to commit to the time needed to fix this, because Sales can't stop selling

Me (8 months ago): hey, this is going to be a problem, but I have a plan on what we need to do to fix it
{no one cares}
Sales (2 weeks ago): THIS IS A PROBLEM WE MUST FIX IMMEDIATELY
{now everyone cares, but only enough to figure out convoluted work arounds to have 'sales ready' drawings}

  • Too many projects (what's normal here, is 5-6 projects for a single, early career engineer normal?)
  • "I need you to update this drawing/design quick, should only take 20 minutes right?"
  • Designs without constraints or dimensions and no information (if it exists, no clue where it is) documenting the design
Maybe I'm too much of an idealist, but I've seen so much of the above, I'm starting to worry that I'll see so much more of this no matter where I go next...hopefully someone can tell me it's better some where.
User avatar
HerrTick
Posts: 207
Joined: Fri Mar 19, 2021 10:41 am
Answers: 1
x 32
x 307

Re: What actually slows down a project?

Unread post by HerrTick »

Recently been getting a barrage of emails from a certain CAD vendor telling me their software will make projects go faster.

No, honey, It won't.
User avatar
HerrTick
Posts: 207
Joined: Fri Mar 19, 2021 10:41 am
Answers: 1
x 32
x 307

Re: What actually slows down a project?

Unread post by HerrTick »

Another project timeline killer--adding or losing people.

Adding people can be worse than losing people.

Manager: "How far behind are we?"
Engineer: "Six weeks."
Manager: "What if we add two more people to the team?"
Engineer: "Sixteen weeks!"
User avatar
JSculley
Posts: 648
Joined: Tue May 04, 2021 7:28 am
Answers: 55
x 9
x 888

Re: What actually slows down a project?

Unread post by JSculley »

HerrTick wrote: Thu Mar 03, 2022 12:52 pm Another project timeline killer--adding or losing people.

Adding people can be worse than losing people.

Manager: "How far behind are we?"
Engineer: "Six weeks."
Manager: "What if we add two more people to the team?"
Engineer: "Sixteen weeks!"
I've repeatedly told the higher ups here that it would be more cost effective to pay people to sit on their hands for 6 months if we have a slow down. Laying off/letting go people who know what they are doing only to hire people who don't six months later is madness.
User avatar
the_h4mmer
Posts: 136
Joined: Mon Jan 31, 2022 6:49 am
Answers: 1
x 106
x 80

Re: What actually slows down a project?

Unread post by the_h4mmer »

HerrTick wrote: Thu Mar 03, 2022 12:52 pm Another project timeline killer--adding or losing people.

Adding people can be worse than losing people.

Manager: "How far behind are we?"
Engineer: "Six weeks."
Manager: "What if we add two more people to the team?"
Engineer: "Sixteen weeks!"
Although I do agree, especially in the context @JSculley brings up, but presently I'm desperate for someone else to join the team. I know it's going to be rough early on, but I need to have someone I can pass off some design work to while I try to repair the PDM vault (all of it).